The escalation in borrowing costs follows Oracle's decision to issue a force majeure notice to Blue Owl Capital, the developer of its New Mexico AI data center built for OpenAI. Oracle is seeking the right to defer lease payments if the site misses its 2028 opening after state officials twice denied permits for a 17 mile gas pipeline required for power. S&P currently rates the company's debt at BBB-, one notch above junk. Morgan Stanley noted that this credit stress is putting other AI infrastructure debt under scrutiny, potentially raising financing costs for other hyperscalers.