The former officials noted that the median time for a new power plant to reach commercial operation grew from under two years between 2000 and 2007 to over four years for projects between 2018 and 2024. They cited data showing China’s share of global knowledge- and technology-intensive manufacturing value added reached 31.5% in 2024, while the US held 20.7%. Additionally, they highlighted that permitting for mining projects averages 5.5 years and up to 8.9 years for contested sites. The legislation would require interregional transmission planning and limit frivolous lawsuits that halt projects indefinitely.