The operator of the UAE’s primary oil fields has clarified when its latest export facility will be ready to move offshore production toward Asian markets without crossing the Persian Gulf. The company indicated that the new West-East pipeline, which will transport crude including Upper Zakum grade to the Fujairah terminal, may become operational as early as the second quarter of 2027.
The 323 mile conduit from Jebel Dhanna to Fujairah will have a capacity of 1.5 MBPD, which will roughly double Adnoc’s export capacity through Fujairah when added to the existing 1.8 MBPD handled by the Adcop line. The project has been under construction since 2024, and Adnoc reported in May that the pipeline was almost 50% complete as work was being accelerated to mitigate risks in the Strait of Hormuz.