Outcome
Estimated likelihoods at publication
6% estimated chance
Will this outcome be true at the resolution cutoff? Assume FERC rejects, suspends, or materially blocks PJM’s request to shorten the required study time for connecting new large loads from two years to 12 months. In this world, the reported proposal does not become an operative PJM tariff or binding process by the cutoff, so the requested mechanism for identifying data-center-driven grid upgrades and billing those companies directly is not implemented during the observation window. The precise cost exposure that would have shifted to large loads is not reported in the supplied evidence.
By 2027-01-02 · Estimated 2026-11-20
Confidence: low
(a) There are 43 days left until the January 2, 2027 resolution cutoff. (b) The status quo outcome is that no FERC order is issued, meaning the strict rejection or suspension criteria are not met by the cutoff. (c) Considering different scopes, while FERC takes months for substantive merits decisions, procedural dismissals such as deficiency letters can sometimes happen slightly earlier. However, they still almost always wait until near the end of the statutory notice period. (d) A No outcome is highly likely because FERC's standard practice is to allow the stakeholder comment period to close (expected mid-January) before issuing any suspension, rejection, or deficiency letter. Without an explicit order issued by January 2, the specific resolution criteria for this scenario are not met [PJM Fast Energization: What Changes for Data Centers | Insights - Build Inc.](https://build.inc/insights/pjm-fast-energization-data-centers). (e) A Yes outcome could theoretically happen if FERC quickly determines the new filing is patently deficient or blatantly violates its October 2026 rejection order [FERC Accepts PJM's Large Load and Large Load Registry Definition but ...](https://www.jdsupra.com/legalnews/ferc-accepts-pjm-s-large-load-and-large-6789352/), prompting a swift procedural rejection or a deficiency letter (requiring material refiling) in late December before the cutoff. (f) In terms of betting odds, I would be willing to pay 6 cents for a YES ticket to win $1. A quick procedural dismissal is slightly more plausible than a rapid merits approval, but it remains highly unlikely before the cutoff. Thus, I assign a 6% probability.
Modeled impact if this scenario occurs. This analysis shows what the model estimates could happen if this scenario occurred, not how likely the scenario is.
For information only. Not investment advice.
Assume FERC rejects, suspends, or materially blocks PJM’s request to shorten the required study time for connecting new large loads from two years to 12 months. In this world, the reported proposal does not become an operative PJM tariff or binding process by the cutoff, so the requested mechanism for identifying data-center-driven grid upgrades and billing those companies directly is not implemented during the observation window. The precise cost exposure that would have shifted to large loads is not reported in the supplied evidence.
These sources support the scenario assumptions. They do not validate the model results.
Source evidence for this Possible Future.
The inputs recorded when the scenario was written.
Current multi-asset market estimates are unavailable.
This estimates the defining event. The modeled impacts depend on the scenario assumptions.