Outcome
Estimated likelihoods at publication
94% estimated chance
Will this outcome be true at the resolution cutoff? Assume that by 2027-03-31 the EU agency publicly terminates, partially terminates, suspends with replacement intent, or materially removes work from the IBM-Atos-Leonardo consortium for the delayed border security system, or publicly launches replacement procurement for substantially the same delayed implementation work. The economic shock is the operational reallocation or prospective reprocurement of government IT/security work, not merely the existence of litigation. The supplied reporting does not provide the contract value, replacement budget, damages amount, or procurement volume, so those magnitudes remain unavailable unless published in the termination or procurement documents.
By 2027-03-31 · Estimated 2026-11-19
Confidence: low
132 days remain. Status quo is effectively YES already: in June 2026 a Sword-led consortium won a €93 million framework contract for design, development, testing, and maintenance of the EES core platform, while the IBM-Atos-Leonardo contract had expired and their transition role ended in 2026 [EU takes EES contractors to court as new consortium takes over border ...](https://www.biometricupdate.com/202611/eu-takes-ees-contractors-to-court-as-new-consortium-takes-over-border-system) [Sword Group: Strategic contract with eu-LISA](https://www.globenewswire.com/news-release/2026/06/04/3306511/0/en/sword-group-strategic-contract-with-eu-lisa.html) [EU's €212M border IT project lands IBM and Atos in legal water](https://www.theregister.com/public-sector/2026/11/10/eus-212m-border-it-project-lands-ibm-and-atos-in-legal-water/5308669). On the narrow scope, the question only needs public termination, scope removal, or replacement procurement for substantially the same delayed work; the new award looks very close to that standard [EU takes EES contractors to court as new consortium takes over border ...](https://www.biometricupdate.com/202611/eu-takes-ees-contractors-to-court-as-new-consortium-takes-over-border-system) [EU takes EES contractors to court as new consortium takes over border ...](https://www.biometricupdate.com/202611/eu-takes-ees-contractors-to-court-as-new-consortium-takes-over-border-system) [Sword Group: Strategic contract with eu-LISA](https://www.globenewswire.com/news-release/2026/06/04/3306511/0/en/sword-group-strategic-contract-with-eu-lisa.html). The main NO case is classification risk: a resolver could view the Sword contract as a normal post-launch follow-on arrangement after EES became operational, rather than a replacement of delayed implementation work [Entry/Exit System fully deployed across the EU - eu-LISA](https://www.eulisa.europa.eu/news-and-events/news/entryexit-system-fully-deployed-across-eu). The YES case is stronger: analysts describe the new group as having taken over the work, and the criteria explicitly prioritize replacement procurement as the strongest implementation change [1c0bd3, 3306511]. Set against related questions and their mutually exclusive alternatives, I put YES at 94%, consistent with those alternatives' probabilities while retaining confidence that this scenario takes precedence. In bet terms, I would buy YES into the low 90s and only feel comfortable selling in the very high 90s.
Modeled impact if this scenario occurs. This analysis shows what the model estimates could happen if this scenario occurred, not how likely the scenario is.
For information only. Not investment advice.
Assume that by 2027-03-31 the EU agency publicly terminates, partially terminates, suspends with replacement intent, or materially removes work from the IBM-Atos-Leonardo consortium for the delayed border security system, or publicly launches replacement procurement for substantially the same delayed implementation work. The economic shock is the operational reallocation or prospective reprocurement of government IT/security work, not merely the existence of litigation. The supplied reporting does not provide the contract value, replacement budget, damages amount, or procurement volume, so those magnitudes remain unavailable unless published in the termination or procurement documents.
These sources support the scenario assumptions. They do not validate the model results.
Source evidence for this Possible Future.
The inputs recorded when the scenario was written.
Current multi-asset market estimates are unavailable.
This estimates the defining event. The modeled impacts depend on the scenario assumptions.