Proceeds will primarily cover cost overruns at the Barber Lake facility, where capital expenditures reached $14 million per MW due to supply chain issues and inflation. The company processed a $359 million change order for labor and materials, expenses it is splitting with a tenant AI lab. Beyond current construction, the firm is targeting "behind-the-meter" power expansion at the same site to unlock 2.5 GW of additional potential.